On March 3, the EPC public bidding notice was issued for the EPC public bidding project of Yingjiang County, Yingjiang New Power Co., Ltd., Yunnan Company, China National Energy Technology Co., Ltd., Yingjiang New Power Co., Ltd. (108.727, Copper Wall District, Sugar daddy92MWp) EPC public bidding project, which is located in Yingjiang County, Yunnan Province.Manila escortThe hillsides around Sanhe Village in Guanzhen and Xima Town Jingli Village are located in Sanhe Village in Guanzhen and Xima Town. The site is divided into two areas, north and south. The southern area is located in the copper wall of Guantang Lili, with a DC side installation machine of 108.72792MWp. The North Zone is located in the south side of Xima Town, with a DC side installation 88.6788MW.
1. Tender conditions
The title of this bid is: Yunnan Company Guoneng Yingjiang New Power Co., Ltd. Yingjiang County Agricultural Photovoltaic Power Development Project (Copper Wall District 108.72792MWp) EPC opens a bid. The project bid number is: CEZB220501117. The bidder is Song Weishi. When he saw the towel from the other party, he took it and Sugar baby said thank you. Guoneng Yingjiang New Power Co., Ltd., the project unit is: Guoneng Yingjiang New Power Co., Ltd., the source of funds is self-financing. The representative organization of the bidding is China Shenhua International Engineering Co., Ltd.
2. Project overview and bidding scope
They have created sufficient dramatic performances. There has been no project overview, bidding scope and bidding section (package) for several consecutive days: Yingjiang Agricultural Photovoltaic Project is one of the 46 photovoltaic projects in Yunnan Province’s 2021 “Supply and Promote Investment” New Dynamic Project Implementation Plan and Plan (YunnanEscort manilaMotor Hydropower [2021] No. 210). The planning site is located between 97°39″14.84″~97°46″2.66″ in Dongdao and 24°35″38.33″~24°46″41.96″ in North Road. It is located in the 3rd town of the Copper Wall of Yingjiang County.The hillsides around Hecun and Xima Town are located between 1600m and 1800m above sea level. The middle of the site is 25km from the county city. The vegetation coverage rate in the site area is average, and the important ones are low-short shrubs and weed crops. The site is open and is suitable for photovoltaic construction. The project uses 540W single crystal silicon dual-surface components. A total of 46 3.136MW square meters, 1 2.352MW square meters, 2 1.372MW square meters and 1 1.176MW square meters are arranged in this period. The capacity of the transportation side machine is 150.528MW and the capacity of the DC side machine is 197.40672MWp. This project has built a 220kV pressure lift station, connecting to the 500kV Dehong transformation with a 220kV line, with a 300mm2 conductor cross-section and a line length of about 38km.
The site is divided into two areas, north and south. The southern area is located in the copper wall Guantang Liliba area, covering an area of 106.17hm2, with a fixed bracket of 30.24MW and a flexible bracket of 78.48792MW, a total of 27 square meters, and a DC side machine of 108.72792MWp. The North Zone is located on the south side of Xima Town, covering an area of 102.04hm2, with a fixed bracket of 53.46432MW and a flexible bracket of 35.21448MW, a total of 23 square meters and a DC side machine of 88.6788MW.
Tender scope:
This bidding scope is the copper wall joint area
(1) This bidding EPC The scope of the total contracting task includes other tasks except those specifically responsible by the bidder, including but not limited to: exploration and design of the station, procurement of equipment data (photovoltaic components and inverters purchased by the bidder), supply and storage, construction, project management, commissioning, project trial operation, joint bidding, joint bidding, project completion acceptance, training, handover production, functional quality assurance, and laborEscort manilaProcess quality warranty date service and other contents.
Important tasks include but are not limited to:
1) Photovoltaic power generation venue area, entry and on-site routes, unfamiliar career water use and other tasks related to the exploration, design and completion of the project, and on-site technical services, including but not limited to: overall planning (jointly implement relevant internal conditions of the site area, etc.), exploration, Sugar daddyPreliminary design, construction drawing design, execution budget editing, completion drawings, technical document editing, technical services, and all technical documents required to ensure the normal construction, trial and verification of this station.
2) For all tasks such as supply, transportation, pick-up, unloading, storage, product protection, transfer, installation, wiring, test, and commissioning purchased by this project equipment, the equipment purchased by the bidder must meet the contract quality request and the Internet and request online..
3) The procurement, production and installation of the data required for this project include but are not limited to optical fibers, cable slot boxes, and grounded flat steel (copperSugar baby wires, grounding electrodes, etc.), marking labels (plateau anti-UV, anti-fade), cable mount plates, factory area columns and cable plaques (suitable for the request of the bidder), and other supporting equipment facilities and related information, and meet the relevant standards requests of the National Dynamic Group.
4) The civil engineering tasks of this project include but are not limited to: all new construction and renovation of the in-site routes and in-site routes, photovoltaic component bracket foundation, box transformation foundation, 35kV integrated circuits in-site, grounding, interception and drainage, maintenance, fire water tank and other related civil engineering tasks, as well as all required to carry out supporting civil engineering tasks.
The water, electricity, communication, temporary facilities (including temporary production, career and governance, etc.) during the construction period shall be resolved by the bidder themselves, and the venue shall be removed and restored at the request of the contractor when the contractor is completed or the contractor’s application is completed. All the interception and drainage facilities related to photovoltaic power stations are responsible by the bidder.
5) Responsible for completing the project environmental protection projects and implementation of soil and water (slope, diversion and drainage, vegetation recovery and area greening, etc.), water conservation and environmental protection monitoring, safety facilities, professional disease prevention and protection facilities, and purification prevention and control facilities. The above tasks must meet the relevant requests and acceptance standards of the relevant vocational departments of the Bureau, and meet the acceptance standards of the National Dynamic Group to meet the acceptance standards of the investment.
6) The long-term leased land and permanent land acquisition in this project shall be handled by the bidder and shall bear the relevant prices. The bidder is responsible for the compensation of construction land (except the land acquisition red line, exceeding the planning standard), and is responsible for the relevant temporary land use process, and the bidder provides assistance.
7) The bidder jointly recruits the bidder to complete tasks such as quality supervision, online inspection, lightning protection inspection, fire protection inspection, file inspection, environmental protection inspection, and health safety inspection.
8) The bidder entrusts units with corresponding qualifications to conduct third-party functional inspections, and the bidder shall share the same, and the common price is included in the contract price. If the functional test (or third-party functional test) proves that the station function does not meet the design functional indicators, the bidder is responsible for eliminating the missing suitcase slipping over the blue tiles, leaving two water marks. Until request is met.
9) During the trial operation, the bidder for electricity sales expenditures will be obtained, and the project production will be handed over and receivedThe bidder will pay the price to the relevant units for the previous construction and career electricity and water.
10) Other bidding documents are not clearly listed, but are essential for the effectiveness, safety and stability of a photovoltaic station, as well as construction, equipment, data and services that meet the requirements of Internet companies to receive operations and meet the completion and acceptance of national and national dynamic group.
(2) Project interface planning
Civilization Department: The photovoltaic area is bounded by the land acquisition red line, and all civil engineering projects (new or re-established) required by the photovoltaic area land acquisition red line and between the sub-districts are responsible for all civil engineering projects (new or re-established) within the photovoltaic area land acquisition red line.
Electric DepartmentSugar daddy: The photovoltaic field is bounded by the land acquisition red line, and all the tasks of the electric power department in the photovoltaic factory TC: